What can be included in an “Architect’s Basic Services” Agreement?

architect

Although an Architect’s scope of work can vary from professional to professional and project to project, this post attempts to define the maximum services Architects can provide.  Talk to your Architect(s) prior to signing any agreement to ensure that their fee proposal properly covers all of the services you are looking to procure.  This post is for information only and not intended as legal advice from the blogger. Appropriate use of the information provided is the responsibility of the reader.

SUMMARY
A client’s unfamiliarity with the process of architectural design should not hinder that client’s comprehension of the phases of design services. This Best Practice introduces first-time clients to the common services of architectural design and the process of design-bid-build. Note: The deliverables listed below are examples of common architectural deliverables for each phase but are not required of AIA members.

SCHEMATIC DESIGN PHASE SERVICES
During the first phase—schematic design—an architect consults with the owner to determine project goals and requirements. Often this determines the program for the project. The program, or architectural program, is the term used to define the required functions of the project. It should include estimated square footage of each usage type and any other elements that achieve the project goals. During schematic design, an architect commonly develops study drawings, documents, or other media that illustrate the concepts of the design and include spatial relationships, scale, and form for the owner to review. Schematic design also is the research phase of the project, when zoning requirements or jurisdictional restrictions are discovered and addressed. This phase produces a final schematic design, to which the owner agrees after consultation and discussions with the architect. Costs are estimated based on overall project volume. The design then moves forward to the design development phase. Deliverables: Schematic design often produces a site plan, floor plan(s), sections, an elevation, and other illustrative materials; computer images, renderings, or models. Typically the drawings include overall dimensions, and a construction cost is estimated. Note: The contract may actually spell out what is to be delivered.

DESIGN DEVELOPMENT PHASE SERVICES
Design development (DD) services use the initial design documents from the schematic phase and take them one step further. This phase lays out mechanical, electrical, plumbing, structural, and architectural details. Typically referred to as DD, this phase results in drawings that often specify design elements such as material types and location of windows and doors. The level of detail provided in the DD phase is determined by the owner’s request and the project requirements. The DD phase often ends with a formal presentation to, and approval by, the owner. Deliverables: Design development often produces floor plans, sections, and elevations with full dimensions. These drawings typically include door and window details and outline material specifications.

CONSTRUCTION DOCUMENT PHASE SERVICES
The next phase is construction documents (CDs). Once the owner and architect are satisfied with the documents produced during DD, the architect moves forward and produces drawings with greater detail. These drawings typically include specifications for construction details and materials. Once CDs are satisfactorily produced, the architect sends them to contractors for pricing or bidding, if part of the contract. The level of detail in CDs may vary depending on the owner’s preference. If the CD set is not 100-percent complete, this is noted on the CD set when it is sent out for bid. This phase results in the contractors’ final estimate of project costs. To learn more about the most common ways owners select a contractor, see Best Practice 05.03.01, “Qualifications-Based vs. Low-Bid Contractor Selection.” Deliverables: The construction document phase produces a set of drawings that include all pertinent information required for the contractor to price and build the project.

BID OR NEGOTIATION PHASE SERVICES
The first step of this phase is preparation of the bid documents to go out to potential contractors for pricing. The bid document set often includes an advertisement for bids, instructions to bidders, the bid form, bid documents, the owner-contractor agreement, labor and material payment bond, and any other sections necessary for successful price bids. For some projects that have unique aspects or complex requirements, the architect and owner elect to have a prebid meeting for potential contractors. After bid sets are distributed, both the owner and architect wait for bids to come in. The owner, with the help of the architect, evaluate the bids and select a winning bid. Any negotiation with the bidder of price or project scope, if necessary, should be done before the contract for construction is signed. The final step is to award the contract to the selected bidder with a formal letter of intent to allow construction to begin. Deliverables: The final deliverable is a construction contract. Once this document is signed, project construction can begin.

CONSTRUCTION PHASE SERVICES
Contract administration (CA) services are rendered at the owner’s discretion and are outlined in the owner-architect construction agreement. Different owner-architect-contractor agreements require
different levels of services on the architect’s part. CA services begin with the initial contract for construction and terminate when the final certificate of payment is issued. The architect’s core responsibility during this phase is to help the contractor to build the project as specified in the CDs as approved by the owner. Questions may arise on site that require the architect to develop architectural sketches: drawings
issued after construction documents have been released that offer additional clarification to finish the project properly. Different situations may require the architect to issue a Change in Services to complete
the project.Deliverables: A successfully built and contracted project.

RESOURCES
More Best Practices The following AIA Best Practices provide additional information related to this topic: 17.02.05 Qualifications-Based vs. Low-Bid Contractor Selection 12.03.02 How Roles Change in Design-Build 11.02.04 Terminology: As-Built Drawings, Record Drawings, Measured Drawings The Knowledge Resources Staff based this Best Practice on definitions in the AIA Contract Documents as well as in the 12th, 13th, and the forthcoming 14th editions of The Architect’s Handbook of Professional Practice.  For More Information on This Topic See also “Defining Services” by Robin Ellerthorpe, FAIA, in The Architect’s Handbook of Professional Practice, 13th edition, Chapter 16, page 515. See also the 14th edition of the Handbook, which can be ordered from the AIA Bookstore by calling 800-242-3837 (option 4) or by email at bookstore@aia.org.

We would love to hear from you on what you think about this post. We sincerely appreciate all your comments.

If you like this post please share it with friends. And feel free to contact us if you would like to discuss ideas for your next project!

Sincerely,
Frank Cunha III
I Love My Architect – Facebook

FC3 ARCHITECTURE+DESIGN, LLC
P.O. Box 335, Hamburg, NJ 07419
e-mail: fcunha@fc3arch.com
mobile: 201.681.3551
direct: 973.970.3551
fax: 973.718.4641
web: http://fc3arch.com
Licensed in NJ, NY, PA, DE, CT.

Advertisements

3 Comments on “What can be included in an “Architect’s Basic Services” Agreement?”

  1. Thorsten says:

    There is definately a great deal to find out about this issue.
    I really like all of the points you made.


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s